Construction Site Planning (3 cr)
Code: TE00BG20-3008
General information
- Enrollment
- 02.07.2025 - 31.07.2025
- Registration for the implementation has begun.
- Timing
- 01.08.2025 - 31.12.2025
- The implementation has not yet started.
- Number of ECTS credits allocated
- 3 cr
- Local portion
- 3 cr
- Mode of delivery
- Contact learning
- Unit
- Engineering and Business
- Campus
- Kupittaa Campus
- Teaching languages
- Finnish
- Seats
- 0 - 50
- Degree programmes
- Degree Programme in Construction and Municipal Engineering
Realization has 11 reservations. Total duration of reservations is 33 h 0 min.
Time | Topic | Location |
---|---|---|
Fri 05.09.2025 time 08:00 - 11:00 (3 h 0 min) |
Työmaasuunnittelu TE00BG20-3008 |
EDU_3002
Henrik muunto byod
|
Thu 18.09.2025 time 11:00 - 14:00 (3 h 0 min) |
Työmaasuunnittelu TE00BG20-3008 |
EDU_3001
Kaarle muunto byod
|
Mon 22.09.2025 time 08:00 - 11:00 (3 h 0 min) |
Työmaasuunnittelu TE00BG20-3008 |
EDU_3002
Henrik muunto byod
|
Thu 02.10.2025 time 13:00 - 16:00 (3 h 0 min) |
Työmaasuunnittelu TE00BG20-3008 |
EDU_2004
Johannes muunto byod
|
Tue 07.10.2025 time 10:00 - 13:00 (3 h 0 min) |
Työmaasuunnittelu TE00BG20-3008 |
LEM_A311
Oppimistila BYOD
|
Thu 23.10.2025 time 16:00 - 19:00 (3 h 0 min) |
Työmaasuunnittelu TE00BG20-3008 |
EDU_2004
Johannes muunto byod
|
Wed 29.10.2025 time 08:00 - 11:00 (3 h 0 min) |
Työmaasuunnittelu TE00BG20-3008 |
EDU_2004
Johannes muunto byod
|
Wed 05.11.2025 time 08:00 - 11:00 (3 h 0 min) |
Työmaasuunnittelu TE00BG20-3008 |
EDU_2004
Johannes muunto byod
|
Mon 10.11.2025 time 10:00 - 13:00 (3 h 0 min) |
Työmaasuunnittelu TE00BG20-3008 |
EDU_4071
Oppimistila muunto byod
|
Thu 20.11.2025 time 11:00 - 14:00 (3 h 0 min) |
Työmaasuunnittelu TE00BG20-3008 |
EDU_1089
Maskulin esitystila byod
|
Mon 24.11.2025 time 11:00 - 14:00 (3 h 0 min) |
Työmaasuunnittelu TE00BG20-3008 |
EDU_3002
Henrik muunto byod
|
Evaluation scale
H-5
Content scheduling
- rakentamisen luvat, viranomaiskatselmukset, muut katselmukset, luovutukset
- tärkeimmät viranomaisilmoitukset, aloituskokous
- työmaan henkilöstö, vastaava, työmaainsinööri, työnjohto, valvojat, koordinaattorit
- turvallisuus, aluesuunnitelma, perehdytys, TR-mittaukset, käyttöönottotarkastukset
- paikalla rakentaminen, elementtirakentaminen, moduulirakentaminen (asennussuunnitelmat)
- hankintasuunnitelma / hankinta-aikataulu / logistiikka / varastointi / työmaan aitaus / taulut
- kalustosuunnitelma, nosturit, nostimet, valaistus, sähkökalusto, sosiaalitilat
- laadunohjaus, aloituspalaverit, mallityöt, suorituksien valvonta, lopputarkastukset
- itselle luovutus ja luovutusvaiheen suunnittelu
- jätteet, kierrätys, pölynhallinta, siivous
- kustannusarvio, tavoitearvio, lopulliset kustannukset
Objective
The student knows the most common work methods on a construction site and their economy, safety and quality at different stages of construction. The student also becomes acquainted with the planning systems of construction site operations and key planning during the construction site, permits, inspections and other obligations applied for, as well as site cooperation.
Content
- Basics of site planning
- Responsibilities of the manager and other supervisors
- Tasks of a site engineer
- Establishment of a construction site
- Site inspections
- Safety-, regional, quality, personnel, equipment and procurement plan
- Target assessment- Reviews- Delivery phase planning- Site meetings
Materials
- opettaja toimittaa luentomateriaalin its-learningiin
- lisäksi kirjaston palvelut
- RT-kortit, rakentamisen teokset, ammattilehdet
Teaching methods
- luennot
- pakollinen harjoitustyö
- pakollinen tentti
- tenttiin osallistuminen harjoitustyöt hyväksyttävästi palauttaneilla
Exam schedules
- tentti opetuskerran viimeisellä luennolla
- tentti perinteinen paperilla vastaaminen
- kurssia ei voi suorittaa ainoastaan harjoitustöillä
- uusintamahdollisuudet 2 kertaa, tammikuussa 2026, helmikuussa 2026
- tenttiin osallistumisoikeus harjoitustyöt hyväksyttävästi palauttaneilla
- uusintatenttiin ilmoittaudutaan opettajalle sähköpostilla, joka kertoo tentin ajankohdan
Pedagogic approaches and sustainable development
- luennot
- harjoitustehtävä
- tentti
Completion alternatives
- pakollinen tentti
- pakollinen harjoitustehtävä
- kurssia ei voi suorittaa ainoastaan harjoitustehtävillä
- tenttiin osallistumisoikeus harjoitustyön hyväksyttävästi palauttaneilla
Student workload
- opiskelijan työn mitoitus 3 * 27 = 81 tuntia
- luennot
- harjoitustehtävä
- tentti
Evaluation methods and criteria
- pakollinen tenttiin osallistuminen
- tentissä 6 kysymystä, joista jokaisen arvo on 5 pistettä
- harjoitustyöt pakollisia
- harjoitustyön palautus its-learning alustalle, ei opettajan sähköpostiin
- tentin osuus arvosanasta 85 %, harjoitustyö + - 15 %
Failed (0)
- tentin pisteet alle 8
- harjoitustyöt palauttamatta hyväksytysti
Assessment criteria, satisfactory (1-2)
- tentin pisteiden arvo 8 - 12,5 = 1
- tentin pisteiden arvo 13 - 17,5 = 2
- harjoitustyöt on palautettu, tarvittaessa korjattu, tehtävän antoon nähden pieniä virheitä, osa asioista huomioimatta
Assessment criteria, good (3-4)
- tentin pisteiden arvo 18 - 22,5 = 3
- tentin pisteiden arvo 23 - 26,5 = 4
- harjoitustehtävät palautettu, tehtäväannon mukaiset asiat huomioitu
Assessment criteria, excellent (5)
- tentin pisteet 27 - 30
- harjoitustyö palautettu ajoissa, harjoitustyö on täysin tehtäväannon mukainen
Further information
- asioista tiedotetaan luentotuntien aikana
- asioista tiedotetaan its-learningin kautta
- harjoitustöitä ei voi toimittaa opettajan sähköpostiin